- Home
- In Our Community
- Construction Projects
- Greenland Southside Integrated Pipe System Water Project
Greenland Southside Integrated Pipe System Water Project

Estimated Dates & Work Schedule
Anticipated End Date: 2026-04-30
Monday through Friday, 7:00 a.m. to 5:00 p.m.*
*In some circumstances, extended hours and weekends may be required. Note: There will be times when 24-hour work operations will be required. JEA will notify residents prior to overnight work.
Project Objective
A contractor working for JEA (Garney Construction) is continuing work on the third and final phase of an overall project to construct a new water transmission pipeline between two major water treatment grids located in JEA’s Duval County service territory. This project will allow JEA the ability to transport excess water supply from the north side of the St. Johns River to the south side of the river to better meet increased potable water demand in the southerly portion of the JEA service area.
Once the new water transmission line is constructed and placed on-line, it will result in a direct offset of water withdrawal from the South Grid. When completed, this project will promote conservation of the Floridian aquifer by lessening JEA's water resource withdrawal demand from its southern raw water well fields.
This third and final phase of the project involves the installation of approximately 41,200 feet of 30-inch ductile iron water main from the JEA electric easement at the end of Validus Drive to the Greenland Water Treatment Plant on Philips Hwy (US 1).
Construction Conditions
Construction will occur in City and State rights-of-way and easements, and within the electric transmission line easement(s) located near homes and businesses. For the safety of crews and the general public, temporary road closures and detours will be required while work progresses along the project route. During the course of this work, access to your residences and businesses will be maintained. JEA will send emails to notify residents directly impacted by these temporary road closures and detours in advance.
Edison East Easement Work 4/14-4-25
Residents in the Edison East community will begin noticing contractor activity next week, as crews start work on installing a new 36-inch HDPE water line. This work will take place within the easement located on the opposite side of the retention pond, south of 9704 Filament Boulevard.
EDISON EAST – WATER LINE
INSTALLATION WORK:
Anticipated Start Date: April 14, 2025*
Estimated Completion Date: April 25, 2025*
Normal Work Hours: 7:00 a.m. to 5:00 p.m.
*Dates and times are highly subject to change.
We apologize for any noise disruptions and appreciate the community’s patience as we complete this phase of the project.
Overall Project Area Map
Planned Water Outages
Some customers may experience minor interruptions to their water service. JEA will notify customers at least 48-hours prior to any planned water outages.
Restoration of the Project Area
Restoration of the project area will begin soon after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.
Greenland Water Treatment Plant (WTP) Update - April 2025
The third and final phase of this project involves construction at the Greenland Water Treatment Plant (WTP) at 6850 Energy Center Drive. Crews are currently pouring the foundation for the new water reservoir.
SIPS Pipeline Install in Easement
Contact
-
If you have any questions about the Greenland Southside Integrated Pipe System Water Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.