Rayford Street Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-01-26
Anticipated End Date: 2023-09-30

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evenings and weekends may be required. 

Project Objective

As part of the Galvanized Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, A contractor working for JEA (T.G. Utility Company, Inc.) replaced and upgraded portions of the water lines on Rayford Street, Owen Avenue and Phyllis Street. By replacing these existing galvanized water lines, customers will experience improved water pressure and increased overall system reliability. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Rayford Street Water Project Map

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new water main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.