- In Our Community
- Galvanized Pipe Replacement Program
- Southside Integrated Pipe System (SIPS)
- Greenland Water Reclamation Facility
- Deercreek Sewer Inspection and Improvement Program
- Construction Terms
- Septic Tank Phase Out
- Move Over Law
- Project Outreach Contact Form
- Site Restoration
- Trenchless Technology
- Meet the Project Outreach Team
- Connecting to the JEA Vacuum Sewer System
- Home
- In Our Community
- Construction Projects
- Shirley Avenue Electric Reliability Project
Shirley Avenue Electric Reliability Project
Estimated Dates & Work Schedule
Anticipated End Date: 2024-04-15
Monday through Friday, 7:00 a.m. to 5:00 p.m.*
*Dates are highly subject to change, and in some circumstances, extended hours and weekends may be required.
Project Objective
JEA and contractor crews completed work on the large scale electric infrastructure improvement project in your area, installing new electric transmission poles, distribution poles, power lines and facilities. This project consisted of upgrading the existing 6.25-mile long circuit between JEA’s Firestone Road and Hamilton Street Substations (see overall project work area map below).
This circuit had recently experienced increases to electric generation and service load due to growth in this area since the system was originally built in 1948. The circuit was upgraded and replaced as it had reached the end of its useful service life for providing consistent and reliable service to this area. The upgraded transmission system will improve your overall electric system reliability and prevent future unplanned power outages in this area.
Construction on this project began in June 2022 along the Shirley Avenue and San Juan Avenue corridor, with the first electric transmission pole installation taking place near the intersection of Shirley Avenue and Vista Avenue (see photo below) on July 25th. Crews installed (14) new transmission poles along Shirley Avenue from Lakeshore Boulevard to Hamilton Street every few days/weeks as the poles arrive from the manufacturer.
Construction Conditions
Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.
Project Maps
Shirley Avenue Work Area Map:
Overall Project Work Area Map:
Project Photos
Restoration of Project Area
Restoration of the project area will begin after the electric lines have been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.
Contact
-
If you have any questions about the Shirley Avenue Electric Reliability Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.