Shirley Avenue Electric Reliability Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-06-13
Anticipated End Date: 2024-04-15

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*Dates are highly subject to change, and in some circumstances, extended hours and weekends may be required.

Project Objective

JEA and contractor crews completed work on the large scale electric infrastructure improvement project in your area, installing new electric transmission poles, distribution poles, power lines and facilities. This project consisted of upgrading the existing 6.25-mile long circuit between JEA’s Firestone Road and Hamilton Street Substations (see overall project work area map below). 

This circuit had recently experienced increases to electric generation and service load due to growth in this area since the system was originally built in 1948. The circuit was upgraded and replaced as it had reached the end of its useful service life for providing consistent and reliable service to this area. The upgraded transmission system will improve your overall electric system reliability and prevent future unplanned power outages in this area.

Construction on this project began in June 2022 along the Shirley Avenue and San Juan Avenue corridor, with the first electric transmission pole installation taking place near the intersection of Shirley Avenue and Vista Avenue (see photo below) on July 25th. Crews installed (14) new transmission poles along Shirley Avenue from Lakeshore Boulevard to Hamilton Street every few days/weeks as the poles arrive from the manufacturer. 

Circuit 663 - Pole Replacement at Shirley and Vista - Photo 5

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Project Maps

Shirley Avenue Work Area Map:

Shirley Avenue Electric Reliability Project Map

 

Overall Project Work Area Map: 

Circuit 663 Project Map

Project Photos

 

Shirley Avenue Project Photo

 

Shirley Avenue Electric Project Photo

Restoration of Project Area

Restoration of the project area will begin after the electric lines have been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.