How to Apply for the Distributed Generation Program

Customers who purchase a renewable generation system for their home or business and wish to connect it to JEA’s power grid must apply for the Distributed Generation Program and follow certain steps to ensure the safety and reliability of the customer and the electric grid.


Please Note:



Interconnection Agreements are required for customers that move into a home with an existing PV or PV + Battery system in order to receive credit for energy sent back to-the-grid. For systems installed after March 31, 2018 please use the "Move-In Existing System - DG" application form in PowerClerk. For systems installed prior to March 31, 2018 that are grandfathered into JEA's Net-Metering program please use the "Move-In Existing System - NM" application form in PowerClerk.


PowerClerk Application


Engineering Standards

Before beginning your application, please review JEA's Distributed Generation Policy (PDF), which details how to connect a renewable generation system to JEA’s grid. Depending on the size of your system, different rates and fees may apply.

Accordion
Accordion Item
Closed Title: Residential
Open Text:

Interconnection application for new solar installation projects on residential systems (some commercial) less than 50 kWh.

Distributed Generation Policy Summary

Generation Range  Energy (kWh) Received (Purchased) from JEA  Energy (kWh) Delivered (Sold) to JEA  Notes 
DG-1 (up to 2 MW) Retail Rate ($0.10283) Fuel Rate ($0.03050)

 

  • Interconnection Agreement required

Solar Bill Example

 

Accordion
Accordion Item
Closed Title: Commercial
Open Text:

Interconnection application for new solar installation projects on residential systems (some commercial) less than 50 kWh.

Commercial Distributed Generation Policy Summary

Generation Range  Energy (kWh) Received (Purchased) from JEA  Energy (kWh) Delivered (Sold) to JEA  Notes 
DG-1 (up to 2 MW) Retail Rate (Varies) Fuel Rate ($0.03050)
  • SS-1 Service may be required > 50 kW
  • Application fee required > 100 kW
  • Interconnection Agreement Required
  • PPA may be required 
DG-2D (Over 2 MW - Distribution Level Connection) Retail Rate (Varies) Avoided Cost (for PURPA Qualifying Facility) 
  • SS-1 Service may be required
  • Application fee required 
  • Interconnection Agreement Required
  • PPA may be required 
DG-2T (Over 2 MW - Transmission Level Connection)  Retail Rate (Varies) Avoided Cost (for PURPA Qualifying Facility) 
  • SS-1 Service may be required
  • Application fee required
  • Interconnection Agreement required 

Solar Bill Example

 


DER Interconnection Requirements

All parallel operating DER interconnections in the JEA electric service territory shall meet the technical interconnection requirements stated in the Parallel Operations and Interconnection of DER Facilities procedure (PDF).


Submit Your Application

PowerClerk Application

Questions

If you have any questions about JEA's Distributed Generation Policy, please contact us:

Email

distgen@jea.com


Phone

904-665-4440