Harrow Court Electric Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-07-19
Anticipated End Date: 2021-09-03

Monday through Friday, 7:00 a.m. to 5:30 p.m. 

Project Objective

A contractor working for JEA (Heart Utilities, Inc.) installed new protective conduit and electric cables along Harrow Court. The contractor installed the new conduit with a technique called horizontal directional drilling (HDD). HDD requires very little excavation, reduces construction duration, and is less disruptive to the surrounding community. This project will help to proactively improve the overall quality and reliability of your electric service. 

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights of way, roads and easements. 

Restoration of Project Area

Restoration of the project area began soon after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 

Map of Work Area

Harrow Court Electric Improvement Project Map