Fulton Cut–Reed Island Electric Relocation Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2025-06-02
Anticipated End Date: 2025-09-26

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

The main goal of this project is to lower a section of existing underground electric conduit and relocate a manhole to place the line deeper underground, ensuring it does not interfere with the excavation of the new canal. This will clear the way for the Harbour Waterway Special District’s canal construction, which will connect to a new harbor linked to the St. Johns River. In the future, this canal may also provide access to a new marina and the canals within the St. Johns Landing Estates neighborhood.

This work will include the relocation of an existing electric manhole and lowering of the underground electric main feeder line along the project route (see map on the reverse). This work will take place primarily on City of Jacksonville property and utility easements, and on Reed Island. 

The contractor will install the new underground conduit with a technique called horizontal directional drilling (HDD). HDD requires very little excavation, reduces construction duration, and is less disruptive to the surrounding area. Once the conduit is installed, JEA contractor crews will then return to install the new electric cables.  

Construction Conditions

During the project, area residents may notice increased vehicular traffic around the project area and some construction-related noise. For the safety of our crews, de-watering pumps to remove ground water may be required prior to excavation. If required, these pump systems will operate continuously throughout the project.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.

Project Work Area Map

Fulton Cut Reed Island Electric Relocation Project