JEA Fulton Cut Transmission Line Clearance Project

 
Item

Century21

Why is this Project Important?

Jacksonville is a hub for global trade located at the crossroads of the nation’s rail and highway network. JAXPORT, Florida’s largest container port, provides jobs, economic impact, and supply chain security for our community. To stay ahead, we need to make room for bigger and taller ships that require a higher clearance.

JEA is working with the City of Jacksonville and JAXPORT to raise the transmission lines crossing the St. Johns River to ensure these larger ships can safely access JAXPORT. Raising the power lines provides an essential community benefit by upgrading critical JEA infrastructure while supporting the more than 15,000 area jobs created or protected by the growth of international container trade in Jacksonville. It’s all about modernizing our community’s capabilities for future generations.

 

Accordion
Accordion Item
Closed Title:What’s Happening with the Project?
Open Text:

The Objective: JEA is raising the six transmission lines that cross the St. Johns River at the Fulton Cut. When completed, the lines will be 225 feet above high tide, giving larger vessels plenty of clearance.

Where It’s Happening: The project area stretches from Blount Island on the north side of the river to Fort Caroline on the south.

Accordion Item
Closed Title:What’s Changing:
Open Text:

The current transmission lines and towers will be replaced with new, taller, stronger structures and includes lightning protection for increased reliability.

Accordion Item
Closed Title:What Are the Benefits?
Open Text:

This project isn’t just about accommodating bigger ships – it’s about supporting Jacksonville’s future. 

Here’s what you can expect:

• Economic Growth: More ships, more jobs and a more resilient supply chain. This keeps JAXPORT – and Jacksonville – thriving.

 Improved Infrastructure: The upgrades strengthen our electric grid, making it more reliable for everyone.

• Modern Technology: Upgrading the electric transmission lines with advanced technology ensures enhanced resiliency and long-term performance.

Accordion Item
Closed Title:What’s the Schedule?
Open Text:

 

Project Phase What's Happening When (Estimate)
Design & Engineering Completing the final design plans Spring 2025
Video/Survey/Mobilization Moving equipment to the site Late June/July 2025
Tower Replacement Building the new pole foundations Summer 2026
Power Line Installation Install new power lines on the newly built structures December 2026
Project Completion Remove the old towers, restore the site and complete construction Summer 2027

 

Item

Fulton Cut Transmission Line Clearance Project Open House

 

March 6, 2025 | 5 - 7 p.m.
Police Athletic League Cafeteria
3450 Monument Road, Jacksonville, FL 32225

On March 6, 2025, from 5:00 PM to 7:00 PM, JEA hosted a public open house to provide information about the project, its benefits to the community, and to answer any questions. Click the link below to view the presentation displayed at the event.

Fulton Cut Presentation

 

Item

JEA Project Outreach will keep you updated as the project progresses.

Construction Activities: We understand that construction can be disruptive, so we’re taking steps to minimize any impacts and keep you informed throughout the process:

Construction Traffic: Due to limited access on the Fort Caroline side of the river, construction vehicles will need to travel through the Beacon Hills & St. Johns Landing neighborhood for the duration of the project. This will result in increased traffic along the designated route.

  • What to Expect: Most of the large equipment will be transported to the work site via barges or helicopter. Construction traffic through the neighborhoods will be restricted to workers, construction equipment, and material deliveries (e.g., concrete, dirt), all of which will follow the designated construction route outlined on this page. Please note that this project will not affect your regular JEA electric service.
  • Traffic Plan: To ensure safety and efficiency, clear signage will be posted to keep construction traffic on designated routes.
  • Extended Work Periods: During certain phases of construction, there may be limited times when extended work hours, including overnight and weekends, are necessary. We will provide advance notice of these periods to minimize any inconvenience.
  • Noise and Visual Impact: Crews will follow strict safety standards and work efficiently to limit noise, dust, and visual disruptions as much as possible. Construction will be limited to the project site.
  • Restoring the Area: Once the work is complete, JEA will repair any landscaping, medians, curbs, sidewalks, asphalt, or sod that may have been disturbed during construction.
  • Staying Updated: JEA Project Outreach will keep you informed with regular updates through flyers, emails, and our dedicated project website, ensuring you always know what’s happening next.
Item

Contact

If you have any questions or concerns regarding the Fulton Cut Transmission Line Clearance Project, please contact us at (904) 665-7500 or email us at ProjectOutreach@jea.com.

Item

 

Project Rendering

Item

FAQ's

Accordion
Accordion Item
Closed Title:What is the cost of the project and who is paying for it?
Open Text:

The project is estimated to cost $117,000,000. Funding is from a combination of a State Grant, and contributions from COJ, JEA, and JaxPort.

Accordion Item
Closed Title:Is this why JEA is raising rates?
Open Text:

No, the rate increase isn't for the higher payments to the city or for raising the power lines. The money for those expenses will come from bond restructuring savings achieved last fall and higher than anticipated electricity sales.

Accordion Item
Closed Title:Why can’t the lines go underground?
Open Text:

An analysis performed early on in the project calculated the cost to be 1.5X the cost of an overhead solution.

Accordion Item
Closed Title:When will you remove the old structures and lines?
Open Text:

Removal of the old line to occur at the end of 2026, with removal of the towers in 2027.

Accordion Item
Closed Title:Will you work at night? If so, how long? Hours?
Open Text:

During concrete pours there is a potential for nightwork, however it is not currently planned.

Accordion Item
Closed Title:Will there be noise associated with the work (metal banging, helicopters)?
Open Text:

There may be helicopter noise at certain times of the day only when erecting/removing towers. During concrete pouring, you may hear/see increased truck traffic throughout the neighborhood.

Accordion Item
Closed Title:Will there be further traffic impacts with the ongoing Ft. Caroline Road construction (FDOT)?
Open Text:

No additional impacts along Ft Caroline Road are anticipated.

Accordion Item
Closed Title:Will JEA work in coordination with their schedule to eliminate the impacts?
Open Text:

 While these projects are separate, we have established alternate traffic routes to avoid FDOT construction zones and are closely coordinating our efforts with FDOT.

Accordion Item
Closed Title:Can the towers be used as artificial reefs?
Open Text:

No

Accordion Item
Closed Title:What happens to the old equipment? Is it recycled?
Open Text:

It becomes property of the Contractor to be disposed.

Accordion Item
Closed Title:Will you be required to remove any fencing or gates?
Open Text:

No gates to be removed.

Accordion Item
Closed Title:How will utilize the gate entrance during major deliveries?
Open Text:

For the south gate, our goal is to provide construction foremen with gate access applications, enabling them to remotely operate the gate for deliveries. The northern gate, which provides access to Reed Island, will remain open during daytime work hours and will be closed outside of these hours, except when opened as needed for potential night work. This plan may be adjusted based on observed impacts to neighborhood traffic patterns.

Accordion Item
Closed Title:Will you sweep the street? How often?
Open Text:

 At the end of each foundation pour, or when otherwise needed the contractor will sweep the construction traffic routes.

Accordion Item
Closed Title:When will you replace any areas impacted during construction?
Open Text:

At the final completion of the project planned for 2027.

Accordion Item
Closed Title:Will there any outages or impacts to JEA’s reliability?
Open Text:

No customer electric outages are anticipated.

Accordion Item
Closed Title:Will JEA and JAXPORT repave the road prior to or following construction?
Open Text:

JEA has no plans to repave the road prior to or following construction. However, consistent with our standard practices, the project team will thoroughly document and record preexisting conditions in the area—including roads, curbs, and grassy areas—before construction begins. Any areas impacted by our work will be restored to their original condition.

Accordion Item
Closed Title:What will JEA do in the event the roadway becomes damaged during construction?
Open Text:

Depending on the extent of any damage, temporary repairs may be performed initially, with final paving and restoration of the road completed after the project concludes.

Accordion Item
Closed Title:How long will we see an increase in truck traffic within the neighborhood?
Open Text:

Increased truck traffic is anticipated from September 2025 through April 2026, though it will not be constant throughout this period. Instead, there will be intervals of relatively low activity followed by periods of heavier traffic, depending on onsite needs. Concrete foundation pours are expected to take approximately 3–4 weeks in total, occurring intermittently rather than consecutively.

Accordion Item
Closed Title:Will there be vibrations caused by the construction? If so, how will these be mitigated?
Open Text:

 Vibrations will be limited primarily to the immediate construction area and are highly unlikely to affect nearby neighborhoods. Some vibrations may occur during foundation installation, particularly if limestone is encountered, but these are expected to be minimal. As a precaution vibration monitors will be installed throughout both the neighborhood and the construction site.

Accordion Item
Closed Title:What type of foundations are being used, how large are these foundations, and how many concrete trucks will be passing through the neighborhood?
Open Text:

We will be installing 18 deep concrete pier foundations on Reed Island. These will range in size from 8 to 11 feet in diameter. The lengths will range from 78 feet to 116 feet. Concrete truck loads will range from 19 to 35 loads per foundation.

Accordion Item
Closed Title:How will heavy equipment be brought into the construction site?
Open Text:

The majority of the heavy equipment (cranes, digging equipment, etc.) will be brough in by barge. Steel for the new towers and poles will be flown in in sections by helicopter from Blount Island. Concrete trucks and smaller equipment that can fit in between the curbs will be driven in through the neighborhood streets.

Accordion Item
Closed Title:Why are concrete trucks being driven in through the neighborhood instead of being barged in?
Open Text:

It is too risky to barge in concrete trucks. Once we start purring concrete for a foundation, we cannot stop until the foundation is fully filled in. If a concrete truck gets held up at the barge or if there are issues with barging, it would compromise the entire operation and possibly result with the abandonment of the foundation.

Accordion Item
Closed Title:Do you plan on illuminating the towers or construction work area?
Open Text:

The new towers will feature light beacons and marker balls that flash at specific intervals used for warning air traffic of the clearance obstacles. These are going to be similar to what is present currently in order to meet Federal aviation requirements. We have no plans of lighting up the towers for other visual effects. The worksite area may be illuminated during the night if construction must proceed into the night hours for critical activates. Currently no nighttime work is planned.

Accordion Item
Closed Title:Can we please ensure that all truck traffic will follow the rules of the road?
Open Text:

We have instructed our contractor to include this requirement in communications with all subcontractors delivering materials through the neighborhood. All subcontractors will be required to comply with traffic laws and adhere strictly to construction speed limits within residential areas.

Accordion Item
Closed Title:Can we leave the south gate opened during construction to avoid additional wear on operable parts and potential backups?
Open Text:

This was discussed with a representative from the HOA as a preference (open during work hours) from JEA/JAXPORT. However, the HOA has currently requested that the gate remain closed, opening only as needed to allow vehicle access. This arrangement is subject to change.