- Home
- In Our Community
- Construction Projects
- 6th Street West Water Improvement Project
6th Street West Water Improvement Project
![](https://www.jea.com/uploadedimages/Images/ConstructionProjectDefaultBanner.jpg)
Estimated Dates & Work Schedule
Anticipated End Date: 2022-10-31
Monday through Friday, 7:00 a.m. to 5:00 p.m.*
*In some circumstances, extended hours and weekends may be required.
*Final restoration of the project area will take place 2-4 weeks after the project has been completed. Dates are weather and supply chain permitting, and highly subject to change.
Project Objective
JEA upgraded and replaced the existing water main on 6th Street West between Melson Avenue and Alfen Street. This section of water main had reached the end of its useful service life and was proactively replaced to ensure the reliability of the water system that serves your neighborhood. This work also included the installation of two (2) new fire hydrants. This project will provide increased water pressure, enhanced fire protection and improved system reliability.
Construction Conditions
Work primarily occurred in City of Jacksonville rights-of-way and easements.
Overall Project Area Map:
Restoration of the Project Area
Restoration of the project area will typically begin 2-3 weeks after the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.
Even Better Power Reliability
JEA's state-of-the-art technology identifies customers and neighborhoods in need of electric reliability improvements.
Contact
-
If you have any questions about the 6th Street West Water Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.