Anvers Boulevard Emergency Sewer Manhole Repair Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-03-25
Anticipated End Date: 2022-04-15

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evening hours and weekends may be required. 

Project Objective

JEA crews completed emergency repairs to a sanitary sewer manhole near 4803 Anvers Boulevard. This repair was necessary to ensure the reliability of the sewer system that serves your neighborhood. Failures to sewer manholes can potentially cause major sewer back-ups, environmental harm and roadway issues. 

Construction Conditions

This work required the removal of ground water with pump systems prior to excavation. 

For the safety of our crews and the general public, we were required to temporarily close Anvers Boulevard between London Bridge Lane and Boy Blue Road while these repairs were completed. 

Project Area Map

Anvers MH

Restoration of the Project Area

Restoration of the project area will take place typically 2-3 weeks after the manhole has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during  construction will be returned to its pre-construction condition.