Bacall Road Sewer Manhole Replacement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-08-17
Anticipated End Date: 2020-09-18

Monday through Friday, 7:00 a.m. to 5:00 p.m. NOTE: In some circumstances, extended hours and weekends may be required. JEA crews will not work on City of Jacksonville holidays (9/7/20).

Project Objective

JEA crews replaced replaced a failing sanitary sewer manhole located near 939 Bacall Road between Regency Drive and Chadron Drive. Failures to sewer manholes can potentially cause sewer back-ups and roadway issues.  

Construction Conditions

Work primarily occurred in the City of Jacksonville rights-of-way and easements. For the safety of our crews and the general public, we were required to temporarily close and detour a portion of Bacall Road while this work was being completed.

Project Area Map

Bacall Road SIP 8.17.20

Restoration of the Project Area

Restoration of the project area will begin after the sewer manhole has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.