Estimated Dates & Work Schedule

Anticipated Start Date: 2020-01-16
Anticipated End Date: 2020-01-27

Monday through Friday, 7:00 a.m. to 5:00 p.m.

Note: Weekends and extended hours may be necessary. 

Project Objective

JEA crews completed emergency repairs to a portion of the sanitary sewer line near 7685 Baymeadows Circle East. This portion of sewer line had reached the end of its useful service life and was repaired to ensure the reliability of the sewer system that serves the neighborhood.  

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way, roads and easements. 

Restoration of Project Area

Restoration of the project area will begin after the sanitary sewer line has been repaired, tested and cleared for use.  Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.