Baymeadows Road Pump Station Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-05-01
Anticipated End Date: 2024-08-31

Monday through Friday, 7:00 a.m. to 6:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

The completion date of this project has been extended due to underground utility conflicts and additional unforeseen circumstances encountered during construction. 

Project Objective

A contractor working for JEA (Ferreira Construction Company) is continuing work on a project to relocate and upgrade the existing sanitary sewer pump station located at 9247 Baymeadows Road.

The objective of this project is to build a new pump station that will upgrade the station’s components and accommodate future growth in the area. Sanitary sewer pump stations are designed to collect wastewater from gravity sewer mains which is then transported to our sewer treatment facilities. This project will ensure the reliability of the sanitary sewer system that serves the neighborhood.  

Construction Conditions

Work is occurring on the JEA property and in City of Jacksonville roads, rights-of-way and utility easements. Residents and businesses may notice increased construction traffic and materials at the pump station site, and there will be some noise associated with this construction.

Restoration of the Project Area

Restoration of the project area will begin soon after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 

Baymeadows Circle Temporary Road Closure & Detour

For the safety of crews and the general public, the contractor will continue to detour traffic on Baymeadows Circle West at Baymeadows Road while construction is completed. The contractor will open the road as soon as it is feasible to do so (late July 2024). Please see the work area and detour map below.

Baymeadows Circle PS Map

Progress Photos

Baymeadows Road PS Project Photo 2Baymeadows Rd Pump Station Progress Photo 1