Broadway Avenue Sewer Main Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2024-01-29
Anticipated End Date: 2024-03-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews repaired sections of a failing sanitary sewer main located on Broadway Avenue from Barber Street to the dead end of Broadway Avenue. This work was necessary to ensure the reliability of the sewer system that serves your neighborhood. Failures to sewer mains can potentially cause major sewer back-ups, environmental harm and roadway issues.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the sewer line has been replaced, tested and cleared for use. Upon completion of the project, existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be restored.  

Project Area Map

Broadway Ave Sewer Improvement Project Map