Chets Creek Boulevard Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-06-06
Anticipated End Date: 2022-08-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews replaced a portion of sanitary sewer force main on Chets Creek Boulevard. This section of sewer main had reached the end of its useful service life and must be proactively replaced to ensure the reliability of the sewer system that serves the area. Sanitary sewer force mains are pressurized sewer pipes used to transport sewage to JEA wastewater treatment plants. Failures to sewer mains can potentially cause major sewer back-ups, environmental harm and roadway issues.  

Construction Conditions

Construction occurred in City of Jacksonville rights-of-way and easements. 

Chets Creek Sewer Improvement Project - Work Area Map

 

 

Restoration of the Project Area

Restoration of the project area typically takes place after the sewer main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.