Dellwood Avenue Emergency Sewer Repair Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-08-13
Anticipated End Date: 2020-10-18

Monday through Friday, 7:00 a.m. to 5:30 p.m. NOTE: In some circumstances, extended hours and evenings will be required. JEA crews will not work on City of Jacksonville holidays (9/7/20). 

Project Objective

JEA crews replaced a portion of failing sanitary sewer main line on Dellwood Avenue between West Street and Acosta Street. This pipe had reached the end of its service life and required replacement to increase the reliability of the sewer system and to prevent future sewer main breaks. Failures to sanitary sewer lines can lead to sewer back-ups and roadway issues.

Construction Conditions

Construction occurred in City of Jacksonville rights-of-way and easements. For the safety of our crews and the general public, JEA was required to temporarily close and detour Dellwood Avenue between West Street and Acosta Street. Residents had access to their homes and were be permitted to drive (with caution) within the project area. 

Work Area and Detour Map

Dellwood Ave Detour Map

Restoration of the Project Area

Restoration of the project area takes place in the 2-3 weeks following the water main improvements. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.