E. 56th Street Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-08-09
Anticipated End Date: 2021-10-31

Monday through Friday, 7:00 a.m. to 4:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA upgraded and replaced a portion of the potable water line on E. 56th Street from Buffalo Avenue to the end of E. 56th Street. These pipes had reached the end of their useful service lives and needed to be proactively replaced to ensure the reliability of the JEA water system in the area. This work also included the installation of one (1) new fire hydrant. This project will provide increased water pressure, improved system reliability and enhanced fire protection to the area.  

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way, roads and easements.

56th St Water Project Map                                             

Restoration of the Project Area

Restoration of the project area typically begins once the water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during construction are returned to its pre-construction condition.