Harts Road - Bluehill Drive Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2014-05-20
Anticipated End Date: 2014-07-31

This project has been completed. Below is the information that was provided to customers prior to the project start date. 

Roads Affected

Bluehill Drive, Bluehill Drive North, Harts Road

Project Objective

JEA crews will be replacing an 800 foot section of failing sanitary sewer force main along a utility easement that stretches from Harts Road near the Springhill Baptist Church to Bluehill Drive (between 11091 Bluehill Drive and 1025 Bluehill Drive North).

This work may require the removal of ground water with a pump system prior to any pipe installation. Sanitary sewer force mains are pressurized pipes used to transport sewage to wastewater treatment plants.

Construction Conditions

Construction will occur in the City’s rights of way and easements. Please observe all construction signs, detours, and general directions provided by the JEA crews working onsite. We apologize in advance for delays caused by this work.

Restoration of Project Area

Restoration of the project area will begin after the sewer main has been installed and the dewatering system removed. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.