Key Haven Boulevard Sewer Manhole Replacement Project

Estimated Dates & Work Schedule
Anticipated Start Date: 2020-02-20
Anticipated End Date: 2020-03-31
Anticipated End Date: 2020-03-31
Normal work hours are Monday through Friday from 7:00 a.m. to 5:30 p.m.
Note: In some circumstances, extended hours and weekends may be necessary. Crews will not work on JEA holidays.
Project Objective
JEA crews replaced a failing sanitary sewer manhole located within the JEA lift station at 10800 Key Haven Boulevard. Failures to sewer manholes can potentially cause sewer back-ups and roadway issues.
Construction Conditions
Construction occurred in the City's streets, rights of way and easements.
Project Area Map
Contact
-
If you have any questions about the Key Haven Boulevard Sewer Manhole Replacement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.