Luana Drive East Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-10-11
Anticipated End Date: 2019-11-30

Monday through Friday, 7:00 a.m. to 5:00 p.m. Note: In some circumstances, weekends and extended hours may be necessary. 

Project Objective

Crews replaced a portion of sanitary sewer main line near 2065 Luana Drive East and 2045 Luana Drive East from the sewer manhole to the JEA lift station. Failures to sewer lines can potentially cause major sewer back-ups and roadway issues. 

Construction Conditions

For the safety of our crews, we removed groundwater prior to excavation using a pumping system that operated continuously during the repair.

Luana SIP

Restoration of the Project Area

Restoration of the project area will begin after the sewer main has been repaired, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.