Marbury Drive Water Main Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-02-03
Anticipated End Date: 2020-04-30

Monday through Friday, 7:00 a.m. to 5:00 p.m. NOTE: In some circumstances, weekend and extended hours may be necessary. JEA crews will not work on JEA holidays (2/17/20). 

Project Objective

JEA crews completed a project to replace the potable water line on Marbury Drive from Kitty Street to Rayben Drive. These pipes had reached the end of their service lives and needed to be proactively replaced to prevent future water main breaks or possible water outages. This project will provide improved water pressure and system reliability. 

Construction Conditions

Construction occurred  in the City’s rights of way, streets and easements.  

Project Area Map

Marbury WIP

Restoration of the Project Area

Restoration of the project area will begin once the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during construction will be returned to its pre-construction condition.