Meadowlea Drive Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-10-17
Anticipated End Date: 2022-12-02

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evening hours and weekends may be required. 

Project Objective

JEA crews replaced a failing sewer line on Meadowlea Drive between Brockett Way and Meadowlea Circle West. This sewer repair was necessary to ensure the reliability of the sewer system that serves your neighborhood. Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues.

Construction Conditions

Work primarily occurred in City rights-of-way and easements. 

Meadowlea Sewer Project Map

Restoration of the Project Area

Restoration of the project area will typically begin 2-3 weeks after the sewer line has been repaired, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.