Pearl Street North Emergency Sewer Main Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-01-10
Anticipated End Date: 2018-05-31

This project has been completed. Below is the information provided to nearby customers. 

Roads Affected

Alder Street, Linwood Avenue, Pearl Street North, Springfield Boulevard

Project Objective

JEA crews replaced a portion of failing sanitary sewer main on Pearl Street North between Alder Street and Linwood Avenue and also replaced individual sewer lateral connections.  

Detour Route and Map

Traffic traveling north on Pearl Street North will turn left on Alder Street, right on Springfield Boulevard, right on Linwood Avenue back to Pearl Street North.  

Traffic traveling south on Pearl Street North will turn right on Linwood Avenue, left on Springfield Boulevard, left on Alder Street back to Pearl Street North. 

Restoration of the Project Area

Restoration of the project area will begin after the sewer main has been tested, cleared for use and the dewatering system removed. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.