POW-MIA Memorial Parkway Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-06-06
Anticipated End Date: 2023-05-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be necessary. 

Project Objective

A contractor working for JEA (T.G. Utility Company) will soon be working in your area to install approximately 10,000 linear feet of water transmission main line on POW-MIA Memorial Parkway (formerly known as New World Avenue) between Waterworks Street and Tea Crates Place. This new line will create a "loop" of the JEA water system that will result in increased water system reliability, improved water pressure and additional fire protection for the area.

Construction Conditions

Work will primarily take place in City of Jacksonville rights-of-way and easements, and there are no road closures or detours anticipated during this project. For the safety of our crews and the general public, please use caution when driving through the work area, and observe any construction signs or general directions provided by the crews working on-site. Please see the work area map below.

POW-MIA Parkway Water Improvement Project Map

Planned Water Outages

Some customers may experience minor interruptions to their water serviceJEA will notify customers at least 48-hours prior to any planned water outagesWe apologize in advance for any inconvenience caused by this construction work. 

Restoration of the Project Area

Restoration of the project area will begin after the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, and sidewalks affected during construction will be returned to its pre-construction condition.