Rodby Drive Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-08-10
Anticipated End Date: 2023-03-31

Monday through Friday, 7:00 a.m. to 4:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews upgraded and replaced portions of the existing water main on Rodby Drive between N. Colbalt Avenue and Bartholf Avenue, on Rodby Court, and on Bartholf Avenue from Rodby Drive crossing Anvers Boulevard. These sections of water main had reached the end of their useful service lives and were replaced to ensure the reliability of the water system that serves your neighborhood. This project will provide increased water pressure and improved system reliability to the area. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Rodby Water Improvement Project

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new water main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.