Shipwatch Drive East Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-11-26
Anticipated End Date: 2024-01-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. JEA crews will not be working on JEA Holidays (12/25, 12/26, 1/1).

Project Objective

JEA crews replaced a portion of the sanitary sewer main near 673 Shipwatch Drive East. This work was necessary to ensure the reliability of the sewer system that serves your neighborhood. Failures to sewer mains can potentially cause major sewer back-ups, environmental harm and roadway issues. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new sewer main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition. 

Map of the Project Area

Shipwatch Drive East Sewer Improvement Project