Martin Luther King Parkway Water Main Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-10-30
Anticipated End Date: 2025-05-30

Dates and times are highly subject to change. In some circumstances, evening and weekend work hours may be required. Crews will not be scheduled to work on JEA Holidays.

Project Objective

A contractor working for JEA (Petticoat-Schmitt Civil Contractors) is continuing work to replace and upgrade approximately 4,550 linear feet of aging water main infrastructure along Martin Luther King (MLK) Parkway on W. 21st Street from Abbott Street to Fairfax Street and from east side of MLK Pkwy and I-95 Interchange to Mars Avenue; and approximately 1,750 linear feet along Myrtle Avenue from W. 15th Street to W. 22nd Street. These sections of pipe have reached the end of their useful service lives and must be proactively replaced to ensure the continued reliability of the water system that serves the community.  

This work will include the replacement of the existing water main and 175 individual water meters and services (to the property line) along the project route. This work will also include the installation and/or replacement of 14 fire hydrants. Once completed, this project will increase water pressure, provide improved system reliability and enhanced fire protection. 

Construction Conditions

For the safety of our crews and the general public, we will be required to temporarily close one travel lane while the new water main is installed. Traffic control flagging personnel may be utilized during working hours to ensure vehicles may safely pass through in both directions. Traffic in both directions will be permitted to drive (with caution) through the project area when crews are not working.

Contractor work hours and maintenance of traffic may change throughout the duration of the project. Temporary road closures may also be required at nearby intersections when crews tie the new water main into the existing water main.

Please observe all construction signs, detours and general directions provided by the crews working on-site. Please see the work area map below.

Temporary Road Closure - Myrtle Avenue

For the safety of crews and the public, W. 21st Street between N. Davis Street and Mars Avenue will be temporary closed and traffic detoured while the contractor installs the new water line. Please see the work area map below.  

W. 21ST STREET – TEMPORARY ROAD CLOSURE:
Anticipated Start Date: Monday, December 9, 2024*
Estimated Completion Date: January 10, 2025* 
Overall Project Estimated Completion Date: May 2025*
*Dates are subject to change. Crews will not work on 11/28, 11/29, 12/24, 12/25, & 1/1.

Residents and/or businesses will be provided access to their driveways and will be permitted to drive (with caution) in the work area. There may be times when driveways are temporarily blocked while crews are working directly in front of homes or businesses. Crews will knock on doors to provide time to move vehicles prior to blocking any driveways. Please observe all construction signs, detours and general directions provided by the crews working on-site.

W. 21st Street Work Area Map

Overall Project Work Area Map

Martin Luther King Parkway Water Main Improvement Project Map

Planned Outages

Some customers may experience minor interruptions to their water service. JEA will notify customers at least 48-hours prior to any planned water outages. We apologize in advance for any inconvenience caused by this construction work. 

Restoration of the Project Area

Restoration of the project area will begin soon after the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.