- Home
- In Our Community
- Construction Projects
- Martin Luther King Parkway Water Main Improvement Project
Martin Luther King Parkway Water Main Improvement Project

Estimated Dates & Work Schedule
Anticipated End Date: 2025-05-30
Dates and times are highly subject to change. In some circumstances, evening and weekend work hours may be required. Crews will not be scheduled to work on JEA Holidays.
Project Objective
A contractor working for JEA (Petticoat-Schmitt Civil Contractors) is continuing work to replace and upgrade approximately 4,550 linear feet of aging water main infrastructure along Martin Luther King (MLK) Parkway on W. 21st Street from Abbott Street to Fairfax Street and from east side of MLK Pkwy and I-95 Interchange to Mars Avenue; and approximately 1,750 linear feet along Myrtle Avenue from W. 15th Street to W. 22nd Street. These sections of pipe have reached the end of their useful service lives and must be proactively replaced to ensure the continued reliability of the water system that serves the community.
This work will include the replacement of the existing water main and 175 individual water meters and services (to the property line) along the project route. This work will also include the installation and/or replacement of 14 fire hydrants. Once completed, this project will increase water pressure, provide improved system reliability and enhanced fire protection.
Construction Conditions
For the safety of our crews and the general public, we will be required to temporarily close one travel lane while the new water main is installed. Traffic control flagging personnel may be utilized during working hours to ensure vehicles may safely pass through in both directions. Traffic in both directions will be permitted to drive (with caution) through the project area when crews are not working.
Contractor work hours and maintenance of traffic may change throughout the duration of the project. Temporary road closures may also be required at nearby intersections when crews tie the new water main into the existing water main.
Please observe all construction signs, detours and general directions provided by the crews working on-site. Please see the work area map below.
Asphalt Repair Operations & Temporary Road Closures - March 31, 2025 to April 3, 2025
The contractor will soon be completing asphalt repairs in portions of the project area and will return in the future to complete final milling and paving of these sections. For the safety of both crews and the public, traffic will be closed and detoured at the following locations:
• The intersections of W. 21st Street and Myrtle Avenue, and W. 22nd Street and Myrtle Avenue
• W. 21st Street between Venus Street and Mars Street
• W. 21st Street between Moncrief Avenue and Myrtle Avenue
• Abbott Street between W. 20th Street and W. 21st Street
These closures will be in effect while the asphalt repair contractor is actively working. Please refer to the map below for the work areas.
Important Resident Request: Residents within the work area boundaries are asked to remove all vehicles, equipment, and trash receptacles from the street until the repair operation is complete. Access to streets and driveways will be limited during the asphalt repair process. Any vehicles left in the street may be towed.
ASPHALT REPAIR OPERATIONS & TEMPORARY ROAD CLOSURES:
Anticipated Start Date: Monday, March 31, 2025*
Estimated Completion Date: Thursday, April 3, 2025*
Hours of Operation: 7 a.m. to 5 p.m.*
This work will occur along the City of Jacksonville right-of-ways and utility easements. Residents and/or businesses will be provided access to their driveways and will be permitted to drive (with caution) around the work area. There may be times when driveways are temporarily blocked while crews are working directly in front of homes or businesses. Crews will knock on doors to provide time to move vehicles prior to blocking any driveways.
Please observe all construction signs, detours and general directions provided by the crews working on-site.
This work will not impact your normal JEA electric, water, or sewer service.
Overall Project Work Area Map
Planned Water Outages
Some customers may experience minor interruptions to their water service. JEA will notify customers at least 48-hours prior to any planned water outages. We apologize in advance for any inconvenience caused by this construction work.
Restoration of the Project Area
Restoration of the project area will begin soon after the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.
Contact
-
If you have any questions about the Martin Luther King Parkway Water Main Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.