- Home
- In Our Community
- Construction Projects
- Point Meadows Substation Electric Reliability Project
Point Meadows Substation Electric Reliability Project
Estimated Dates & Work Schedule
Anticipated End Date: 2017-05-31
This project is substantially complete. Below is the information provided to customers prior to the project start date.
Project Objective
The City of Jacksonville is experiencing substantial growth on the Southside near the St. Johns Town Center and the East Beltway I-295 corridor. To keep up with the electric demand and maintain the reliability of our electric system, JEA is continuously investing in projects to upgrade and expand our electrical grid.
Construction is underway at the new Point Meadows Electric Substation which will be located along an existing transmission line easement just off Point Meadows Drive near Gate Parkway Boulevard.
When completed, this new substation will substantially improve the reliability of the electrical system in your area as well as reduce the chances of overloading a circuit which can lead to unplanned power outages.
Customers in the area will not experience any electric service interruptions as a result of this construction project.
Construction Conditions, Substation Design and Area Restoration
Contractors have already started work to prepare the site for the construction of the substation. This work includes the removal of several abandoned buildings, trees, shrubs and grass. This particular substation was designed with a smaller footprint than our standard substations in consideration of nearby wetlands.
As part of the project, JEA will fence and landscape outside the substation. The landscape plans include the addition of 11 cathedral oak trees, 9 bald cypress trees, 8 red maple trees, 10 long leaf pine trees and 2 southern red cedar trees to offset the trees removed for the construction of the station. JEA will install LED “down lighting” that is specifically designed to light the substation and not the surrounding area.
When completed, the entrance to the substation will be located at 7754 Point Meadows Drive adjacent to an existing detention pond and the Point Meadows Professional Building.
The below map depicts project detail at the site and an overall project map is located to the right.
Check out our progress photos below!
Substation construction as of September 29, 2016:
Substation completion:
Watch a video about this project!
Future Transmission Line Project & Electrical Feeder Upgrades
JEA will also be constructing additional transmission power lines along the existing corridor that will help serve the new electric substation and surrounding area. We will also be upgrading electrical feeders and installing underground conduit along Gate Parkway and Point Meadows to the entrance of the substation. This work is scheduled to begin in January of 2017.
Contact
-
If you have any questions about the Point Meadows Substation Electric Reliability Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.
Related Links
-
Electric Facilities
JEA operates five power plant sites in Jacksonville, has an ownership interest in a power plant in Georgia, and purchases power locally from a solar field and a landfill gas facility. Diversity in fuel mix is very important in providing reliable, economical and environmentally-sound electricity.
-
Electric Systems
JEA is proud of its Electric System and its reputation as one of the nation’s exemplary municipal service providers. Our existing generation capacity is 3,747 MWs and our generation fleet contains a diverse resource mix.