Woodlawn Avenue Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-11-13
Anticipated End Date: 2024-09-30

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

As part of the Galvanized Pipe Replacement Program to modernize more than 200 miles of JEA’s existing potable water distribution system, a contractor working for JEA (United Brothers Development) is working in your area to replace and upgrade portions of the water lines on Woodlawn Avenue, Osceola Street, Claude Street, Calvin Street, Clemente Drive, Lewis Street, Goodwin Street and Lime Street.  

These pipes are approaching the end of their useful service lives and are being proactively replaced to ensure the reliability of the JEA water system in the area. When completed, this project will provide increased water pressure, enhanced fire protection and improved system reliability. 

Construction Conditions

For the safety of our crews and the general public, there will be times when roads will be temporarily closed to thru traffic while crews are installing the new water lines. Please see the overall project area map below. 

Residents, businesses and business patrons will have access and will be permitted to drive (with caution) within the project area. There will be times when driveway access is limited while crews are working directly in front of homes and businesses. Please observe all construction signs, detours and general directions provided by the crews working on-site. We apologize in advance for any inconvenience caused by this construction work.  

Paving Notification - Temporary Road Closures Required

The contractor will soon begin paving portions of the remaining streets in the project area where water lines were recently installed. For the safety of crews and the public, we will be required to temporarily close and detour traffic on Calvin Street, Claude Street, Lewis Street and Woodlawn Avenue while paving is completed. JEA encourages residents to plan ahead for traffic delays, and limit on-street parking during this time. Please see the work area map below. 

PAVING DATES & TIMES - TEMPORARY ROAD CLOSURES:

Anticipated Start Date: June 11, 2024*

Estimated Completion Date: June 14, 2024*

Work Hours: 7:00 a.m. to 5:00 p.m.*

*Dates and times are weather permitting and highly subject to change.

Woodlawn-Clemente WIP Paving Map

 

 

Restoration of the Project Area

Restoration of the project area will begin soon after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 