Upcoming Procurement Opportunities at JEA

The following contract opportunities will be advertised in the next six (6) months. JEA anticipates this advertisement schedule and reserves the right to add, change or eliminate offerings as required. For additional information or questions, please email bids@jea.com.
For additional information or questions, please email bids@jea.com.

THIS IS NOT AN ADVERTISEMENT

Project Name Project Type Estimated Advertisement Estimated Project Start Estimated Project Duration (Months) Scope Estimated contract Value
St. Johns Forest Wells Engineering (CCNA) March 2019 September 2019 9 Design of 4,500 lf of 30" Raw WM $800,000 - $1,300,000
Construction, Engineering and Inspection (CEI) Services Staffing Services April 2019 October 2019 60 Provide CEI staffing N/A
STPO Biltmore C Septic Tank Phase Out Construction April 2019 June 2019 20 Provide CEI staffing $8,000,000 - $9,000,000
STPO Biltmore C Septic Tank Phase Out Construction April 2019 June 2019 20 Provide CEI staffing $8,000,000 - $9,000,000
Lakeshore WTP - Reservoir Rehabilitation Construction April 2019 July 2019 4 Upgrade Wellhead and Replace Pump $100,000-$500,000
LDP Program - Walnut St Trunkline Replacement: 32nd St PS to 16th St E Construction May 2019 July 2019 19 Installation of 3000 LF of 36" PVC Gravity Sewer $5,000,000-$6,000,000
LDP Program - Palm Avenue WM Replacement Construction May 2019 July 2019 6 Installation of 640 LF 8" CLDI WM Open Cut / 1120 LF 12" CLDI WM Open Cut $500,000 - $1,000,000
Emory Circle - From Cornell Rd along Rollins Ave and Tulane Ave to Emory Circle Construction May 2019 August 2019 6 Installation of 2322 LF 8" PVC WM Open Cut / 4435 LF PVC WM Open Cut $500,000 - $1,000,000
Greenland WRF - 6.0 MGD Construction (CMAR) May 2019 October 2019 6 CMAR (Pre-Construction Services): not including GMP $500,000 - $1,000,000
Nassau Regional WRF Projects Construction (CMAR) May 2019 October 2019 20 CMAR (Pre-Construction Services): not including GMP $500,000 - $1,000,000
LDP Program - King St and Shircliff Way WM Replacement Construction (CMAR) May 2019 August 2019 6 Installation of 1000 LF 8" CLDI WM Open Cut / 300 LF 10" CLDI WM Open Cut $100,000 - $300,000
Bradley Road Pump Station Electrical & Associated Improvements Construction May 2019 August 2019 21 Installation of 30 MGD Booster Pump Station Improvements $6,000,000 - $7,000,000
Buckman - 5307 Buffalo Ave - Class III/IV Construction June 2019 September 2019 18 Rehabilitation of 7 MGD Pump Station $4,000,000 - $5,000,000
Lofton Oaks WTP Improvements Construction June 2019 September 2019 11 Installation of 2,000,00G GST / HSP / Yard Piping $2,000,000 - $3,000,000
Southwest WWTF Expansion from 14 to 18 MGD Construction (CMAR) June 2019 April 2019 21 CMAR (Pre-Construction Services): not including GMP $1,000,000 - $2,000,000
Buckman Biosolids Conversion Projects Construction (CMAR) June 2019 December 2019 23 CMAR (Pre-Construction Services): not including GMP $500,000 - $1,000,000
Owens Rd - Ranch Rd to Max Leggett Pkwy - New - W Construction (CMAR) July 2019 October 2019 8 Design of 5000 LF 16" PVC Water Main Open Cut / 1200 18" HDPE Directional Drill $800,000 - $1,300,000
Arlington East WRF Upgrades Construction (CMAR) July 2019 December 2019 15 CMAR (Pre-Construction Services): not including GMP $500,000 - $1,000,000
Gate Parkway to Burnt Mill Rd - Trans - R Construction July 2019 October 2019 9 Installation of 7400 LF 8" PVC RWM Open Cut / 500 LF 4" PVC RWM Open Cut $1,000,000 - $2,000,000
E 1st St Main St to E 4th St - Raw Water - New - W Construction July 2019 October 2019 21 Installation of 4000 LF 30" CLDI Pipe Class 150 Open Cut $3,000,000 - $4,000,000
TWMP - Main St WTP - 1st St to Franklin St - Trans - W Construction July 2019 October 2019 21 Installation of 7500 LF of 36" TWMP WM / 3000 LF of 30" Raw WM / 1200 LF of 20" Raw WM $6,000,000 - $7,000,000
4511 Spring Park Rd Lift Station Construction August 2019 October 2019 14 Installation of Odor Control Sys: Biotrickling Filter / Aux Diesel Pump / Electrical Resiliency / 14" Mag Meter with Bypass $3,000,000 - $4,000,000
Greenland WTP - Expansion from 6.0 to 9.0 MGD Construction August 2019 May 2019 4 Installation of WTP Improvements / 1-HSP / 1 MG GST / 750 KW Generator $3,000,000 - $4,000,000
DII - 11308 Harts Rd Construction August 2019 October 2019 13 Installation of 600amp 480V 3-Phase Main Breaker / 7 Section MCC / Transfer Switch / Control-Comm Equipment $1,000,000 - $2,000,000
DII - Robena Rd Booster WW PS Construction August 2019 October 2019 13 Installation of 3500 gpm Booster Pump Station / 800 LF 20" PVC FM Open Cut $2,000,000 - $3,000,000
Buckman Biosolids Conversion -Vacuum Truck Unloading Facility Construction August 2019 October 2019 12 Installation of Vacuum Truck Unloading Facility $3,000,000 - $4,000,000
Buckman WRF - Blower System Improvements Construction September 2019 December 2019 12 Installation of Aeration Blowers and Aeration System $4,000,000 - $5,000,000
Ponte Vedra Blvd 6" Cast Iron Replacement Construction September 2019 December 2019 6 Installation of 9400 LF 10" HDPE WM by Pipe Bursting $2,000,000 - $3,000,000
Project Name Project Type Estimated Advertisement Estimated Project Start Estimated Project Duration (Months) Scope Estimated contract Value