7th Street West Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-01-12
Anticipated End Date: 2022-02-25

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews repaired a failing sanitary sewer line on 7th Street W. between St. Clair Street and Huron Street. This repair was necessary to ensure the reliability of the sewer system that serves the neighborhood.  Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues.  

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way and easements. 

W 7th Ave SIP Map

 

 

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.