Abilene Road Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-04-06
Anticipated End Date: 2023-05-12

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews replaced a portion of sanitary sewer main near 10519 Abilene Road. This section of sewer main had reached the end of its useful service life and was replaced to ensure the reliability of the sewer system that serves your neighborhood. Failures to sewer mains can potentially cause major sewer back-ups, environmental harm and roadway issues.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Project Work Area Map

Abilene Road Sewer Improvement Project - Map of Work Area

Restoration of Project Area

Restoration of the project area typically begins 2-3 weeks after the sewer main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.