Alderfer Springs Drive Emergency Sewer Manhole Repair Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-04-30
Anticipated End Date: 2019-05-07

Monday through Friday, 7:00 a.m. to 5:00 p.m.

NOTE: In some circumstances, extended hours and weekends may be necessary. 

Project Objective

JEA repaired a failing sanitary sewer manhole on Alderfer Springs Drive near Mill Hopper Road.  Failures to sewer lines can potentially cause major sewer back-ups and roadway issues.   

Construction Areas

Construction occurred in the City’s streets, rights of way and easements. For the safety of our crews and the general public a portion of Alderfer Springs Drive at the intersection of Mill Hopper Road was temporarily closed during construction.  

Restoration of the Project Area

Restoration of the project area will begin after the sewer line has been repaired, tested and cleared for use. Upon completion of the project, existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be restored.  

Alderfer Springs Drive Emergency Sewer Repair Project