Arrow Lakes Drive East Emergency Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2015-03-31
Anticipated End Date: 2015-04-10

This project has been completed. Below is the information provided to customers prior to the project start date.


 

Roads Affected

Arrow Lakes Drive East, Tree Lake Drive

Project Objective

JEA crews will be making emergency repairs to a sanitary sewer manhole located on Arrow Lakes Drive East near Tree Lake Drive.  

Failures to sewer manholes can potentially cause major sewer back-ups and roadway issues. JEA crews will be working as quickly and safely as possible to make the necessary repairs.  

Construction Conditions

Construction will occur in the City’s rights of way and easements.  Please observe all construction signs, detours, and general directions provided by the JEA crews working onsite.  We apologize in advance for delays caused by this work.

Restoration of Project Area

Restoration of the project area will begin after the sewer manhole has been installed and cleared for use.  Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.