Baymeadows Circle East - Emergency Sewer Repair Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-09-02
Anticipated End Date: 2020-10-31

Monday through Friday, 7:00 a.m. to 5:00 p.m. NOTE: Weekends and extended hours may be necessary. JEA crews will not work on City of Jacksonville holidays (9/7/20). 

Project Objective

JEA crews replaced two (2) failing sanitary sewer manholes near 7927 Baymeadows Circle East. These manholes were replaced to ensure the reliability of the sewer system that serves the area. Failures to sewer manholes can potentially cause major sewer back-ups and roadway issues.  

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way, roads and easements. 

Project Area and Detour Map

Baymeadows Circle East 9.2.20

Restoration of the Project Area

Restoration of the project area began after the sanitary sewer manholes were installed, tested and cleared for use.  Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction were returned to its pre-construction condition.