Bigtree Circle West Emergency Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-11-02
Anticipated End Date: 2020-12-04

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*NOTE: In some circumstances, evening and weekend work may be required. 

Project Objective

JEA crews replaced a failing sanitary sewer manhole and sewer main near 10415 Bigtree Circle West. The manhole and sewer had to be replaced to ensure the reliability of the sewer system that serves the neighborhood. Failures to sewer mains and manholes can potentially cause major sewer back-ups, harm to the environment and roadway issues.

Construction Conditions

For the safety of our crews and the general public, we were required to temporarily detour traffic around the work area while the work was being completed (see map below). 

Big Tree Circle W MH

Restoration of the Project Area

Restoration of the project area will begin after the sanitary sewer manhole has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.