Buffalo Avenue Water Main Improvement Project
Estimated Dates & Work Schedule
Anticipated End Date: 2019-06-28
Monday through Friday, 7:00 a.m. to 5:00 p.m. NOTE: In some circumstances, night, weekend and extended hours may be necessary. JEA crews will not work on City of Jacksonville holidays.
Project Objective
JEA replaced and upgraded a portion of the existing water main on Buffalo Avenue between 44th Street East and 50th Street East. This work included the installation of three (3) new fire hydrants. This project will provide increased water pressure, provide improved system reliability and fire protection.
Construction Conditions
Construction occurred in the City’s rights of way, streets and easements.
Project Area Map
Restoration of the Project Area
Restoration of the project area will begin once the water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during construction will be returned to its pre-construction condition.
Even Better Power Reliability
JEA's state-of-the-art technology identifies customers and neighborhoods in need of electric reliability improvements.
Contact
-
If you have any questions about the Buffalo Avenue Water Main Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.