Bunker Hill Roadway Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-08-30
Anticipated End Date: 2018-11-16

Note: Start and completion dates are subject to change.

Project Objective

A contractor working for JEA has completed the necessary paving repairs along Bunker Hill Road from Concord Boulevard West to Lake Forest Boulevard. This work included the milling of the asphalt, the removal and replacement of the existing sub-base, the repaving of the road and restriping as required.

Construction Conditions

Following the completion of the project, any driveways, curbs, sidewalks, sod, irrigation or landscaping unintentionally damaged during construction will be replaced or repaired.

Partial Road Closure

JEA’s was required to close Bunker Hill Road from Concord Boulevard West to Lake Forest Boulevard to thru vehicular traffic Monday through Friday from 8 a.m. to 5 p.m. during the work. Traffic was temporarily detoured around the work area.

Bunker Hill Roadway Improvement Project - Detour Map