Cesery Boulevard Electric Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-03-12
Anticipated End Date: 2019-06-30

Monday through Friday, 7:00 a.m. to 5:00 p.m. (weather permitting). NOTE: In some circumstances, extended hours and weekends may be required. 

Project Objective

A contractor working for JEA (Henkels & McCoy) completed a project to replace and upgrade the electric transmission poles along Cesery Boulevard. When completed, this project will provide our customers with improved electric reliability.  JEA did not complete any work at the individual electric meter that serves individual homes or businesses. 

Construction Conditions

Residents can expect anywhere between 5-8 large utility trucks in the area depending on the planned work activity.  Power poles will be temporarily dropped off or staged in the public right of way portion of your yard until they can be installed.  Several poles may be moved back at least 4-feet from the curb, road, or sidewalk to conform to current JEA standards for road clearances.  Most poles replaced will remain immediately adjacent to the existing pole.  

Once the poles have been placed in the ground, crews will then install the equipment on the poles followed by pulling the new electric wires between the new poles.  JEA will leave the old power poles in place until AT&T and Comcast change their facilities over to the new poles.  Once this work occurs, JEA will return to remove the old poles.

JEA may require some detours and lane closures while this work is completed.  The Jacksonville Sheriff’s Office may be utilized to help direct traffic around the construction area.  Any roads, curb, grass, driveway, sidewalk, or sod unintentionally damaged    during  construction will be replaced at the end of the project.

Restoration of the Project Area

Any roads, curb, grass, driveway, sidewalk, or sod unintentionally damaged during construction will be restored to pre-construction conditions once the project has been completed.