Estimated Dates & Work Schedule
Anticipated Start Date: 2015-01-30
Anticipated End Date: 2015-05-31
Anticipated End Date: 2015-05-31
This project has been completed. Below is the information provided to customers prior to the project start date.
Roads Affected
Cherokee Street, Edison Avenue, Fitzgerald Street, McCoy's Creek Boulevard
Project Objective
JEA will be replacing and upgrading the existing water main on Cherokee Street from Edison Avenue to Fitzgerald Street/McCoy’s Creek Boulevard. This work will also include the installation of new individual water services (to the property line) and one (1) new fire hydrant. When completed, this project will increase water pressure, and provide better system reliability.
Construction Conditions
Construction will be done in the City’s rights of way and easements. There will be times when your road will have limited access while the water main is being installed. JEA will maintain the flow of traffic, although residents may experience some minor delays.
Water Outages
Some customers will experience minor interruptions to their water service. JEA will notify customers 48 hours prior to any planned outages. Residents may also experience a brief (10 to 15 minutes) outage while crews transfer your home from the old water service to the new water service.
Restoration of Project Area
Restoration of the project area will begin once the water lines are installed and have been tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during construction will be returned to its pre-construction condition.
Even Better Power Reliability
}
/uploadedImages/jeacom/SiteInterceptAdCEMI5.jpg
JEA's state-of-the-art technology identifies customers and neighborhoods in need of electric reliability improvements.
Contact
-
If you have any questions about the Cherokee Street Water Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.