Estimated Dates & Work Schedule

Anticipated Start Date: 2020-05-18
Anticipated End Date: 2020-10-30

Monday through Friday, 7:00 a.m. to 5:00 p.m. 

Note: In some circumstances, evening and weekend work hours may be required. Crews will not work on City of Jacksonville holidays (5/25, 7/3, 7/4, 9/7). 

Roads Affected

Amberwood Court, Bentridge Court, Cayuga Trail South, Chason Court, Chason Road East, Chason Road West, Chimney Oak Drive, Copperfield Circle North, Copperfield Circle South, Copperfield Circle West, Crosswind Court, Crosswind Road, Staghorn Road

Project Objective

A contractor working for JEA (Hearts Utilities, Inc.) installed new conduit, cabling, transformers and PVC manholes in the Chimney Lakes community.  This work will help to improve the overall quality and reliability of the electric service for the area.  

Construction Conditions

Most of the construction activities occurred in the city right-of-way portions, usually closer to the sidewalk or road. Any grass, concrete, asphalt, or sprinklers damaged during the work is replaced after the completion of the project. Please see the project area map below.

Chimney Lakes EIP Map

Restoration of the Project Area

Restoration of the project area will begin once the lines have been installed, tested and cleared for use.  Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.