Cimarrone Golf and Country Club Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-12-04
Anticipated End Date: 2024-02-29

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

A contractor working for JEA (Vortex Companies) rehabilitated multiple sanitary sewer manholes in the Cimarrone Golf & Country Club community. These manholes were proactively rehabilitated to ensure continued reliability of the sewer system that serves the neighborhood. Failures to sewer manholes can potentially cause major sewer back-ups, environmental harm and roadway issues. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the project has been completed. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition. 