Citra Avenue Water Main Installation Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-01-28
Anticipated End Date: 2019-04-30
Normal working hours are Monday through Friday, 7:00 a.m. to 5:00 p.m. In some circumstances, weekends and extended hours may be required. 

 

Roads Affected

Project Objective

Working in partnership with the City of Jacksonville, JEA completed installation of a new potable water line on Citra Avenue. The funding for this project was provided by the City of Jacksonville.

JEA crews installed a new 4‐inch water line in the City right‐of‐way along Citra Avenue from Wiley Road to the end of Citra Avenue. 

Connecting to the New JEA Water Line

Property owners that live along the pipe route that are interested in obtaining water service will be responsible for paying all JEA connection fees, on‐site plumbing costs and obtaining associated permits required to make the connection from individual homes to JEA’s water line located in the right‐of‐way.

JEA will install a water meter at each property once connection fees are paid. More information will be provided by JEA to eligible property owners once the water line has been installed and cleared for use.

Construction Areas

Construction occurred in the City’s rights of way and easements. 

Restoration of the Project Area

Restoration of the project area will begin once the water line is installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curbs, driveways or sidewalks affected during construction will be returned to its pre‐construction condition. Additional information will be provided to the community throughout the project.

Project Area Map

Citra Avenue Water Main Installation