Clairmont Road Water Main Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2013-11-18
Anticipated End Date: 2013-12-13

This project has been completed. Below is the information that was provided to customers prior to the project start date. 

Roads Affected

Clairmont Road, Paul Avenue

Project Objective

JEA crews will be installing a new 2-inch potable water main on Clairmont Road from Paul Avenue to the end of the dead end street. Residents along Clairmont Road that reside within the project limits will be contacted personally by representatives from JEA to discuss connection options for each individual property.

Construction Conditions

Construction will be done in the City’s rights of way and easements. There will be times when roads will have limited access while the water main is installed but the flow of traffic will be maintained.

Sections of driveways may be removed and replaced to install the pipe. Residents will be notified in advance by JEA crews to allow for removal of vehicles prior to driveway construction.

Restoration of Project Area

Restoration of the project area will begin once the water lines are installed and have been tested and cleared for use. Upon completion of the project, any existing grass, curb, swales, driveways or sidewalks affected during construction will be returned to its pre-construction condition.