Club Duclay Drive Emergency Sewer Repair Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-07-06
Anticipated End Date: 2020-07-24

Monday through Friday, 7:00 a.m. to 5:30 p.m.*

NOTE: In some circumstances, evening and weekend work hours may be necessary. 

Project Objective

JEA crews completed emergency repairs to a portion of the sanitary sewer line on Club Duclay Drive between Augo Lane and Adventure Lane. This portion of sewer line had reached the end of its useful service life and had to be repaired to ensure the reliability of the sewer system that serves the area. Failures to sewer lines can potentially cause major sewer back-ups and roadway issues.  

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights of way, roads and easements.  

Club Duclay Detour Map

Restoration of the Project Area

Restoration of the project area takes place once the new sewer main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction are returned to its pre-construction condition.