Commonwealth Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-06-10
Anticipated End Date: 2019-07-12

Start and completion dates are subject to change and in some circumstances occasional night and weekend work hours may be necessary.

Project Objective

JEA crews completed work to replace 525 linear feet of the existing 8-inch gravity sewer main and manholes within a 25 foot easement along the roadway from 5700 Commonwealth Avenue to 5638 Commonwealth Avenue. 

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights of way, roads and easements. The contractor was required to temporarily close one lane eastbound of Commonwealth Avenue to complete the installation of the new sanitary sewer main. These lane closures were necessary for the both the safety of the workers and the general public. 

Restoration of the Project Area

Restoration of the project area will begin after the new sewer main has been installed, tested and cleared for use.  Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition. 

Commonwealth Sewer Improvement Project - Map