Creighton Bluff Lane Water Main Extension Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-05-30
Anticipated End Date: 2023-08-04

Monday through Friday, 7:00 a.m. to 6:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews extended the existing water main on Creighton Bluff Lane. This water project is complete and was paid for at the request of a property owner on Creighton Bluff Lane.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements. 

Project Area Map

Creighton Bluff Lane Water Main Extension Project - Work Area Map

Restoration of Project Area

Restoration of the project area typically begins 2-3 weeks after the water main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.