Deercreek Sanitary Sewer Manhole Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-03-27
Anticipated End Date: 2023-07-29

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

A contractor working for JEA (Engineered Spray Solutions) has completed a project to rehabilitate multiple sanitary sewer manholes in the right-of-way areas within the Deercreek community. These manholes needed to be proactively rehabilitated to ensure continued reliability of the sewer system that serves the neighborhood. Failures to sewer manholes can potentially cause major sewer back-ups, environmental harm and roadway issues.  

Construction Conditions

The majority of this work was completed in utility easements within the Deercreek community. Please see the map below for manhole repair locations.

Map of Manhole Repair Locations

Deercreek Sanitary Sewer Manhole Improvement Project - Map of Manhole Repair Locations

Restoration of Project Area

Restoration of the project area typically begins soon after the sewer manholes have been rehabilitated, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.