Franklin Street Water Main Extension Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2024-02-12
Anticipated End Date: 2024-03-29

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews extended the existing water main on Franklin Street near the intersection of Oakley Street. This water project was completed and paid for at the request of a property owner on Franklin Street. 

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new water line has been installed, tested and cleared for use. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition. 

Project Work Area Map

Franklin Street Water Main Extension Project - Map