- Home
- In Our Community
- Construction Projects
- Hemlock Street Electric Improvement Project
Hemlock Street Electric Improvement Project
![](https://www.jea.com/uploadedimages/Images/ConstructionProjectDefaultBanner.jpg)
Estimated Dates & Work Schedule
Anticipated End Date: 2022-05-31
Monday through Friday, 7:00 a.m. to 5:00 p.m.*
*In some circumstances, extended hours and weekends may be required.
Project Objective
JEA replaced and upgraded the main electric feeder line that serves the Hemlock Street area. We
also upgraded and replaced several of the power poles along Hemlock
Street that have reached the end of their useful service lives and needed to be
replaced.
Once completed,
this work will allow for future growth in the area, while increasing the
amperage capacity of the power line, thereby reducing chances of overloading
the circuit which can lead to unplanned power outages.
Construction Conditions
The pole relocation portion of this
project will allow JEA to maintain proper clearances in preparation for a
future City of Jacksonville sidewalk improvement project along Hemlock Street.
The new poles were installed approximately 2-3 feet toward private property,
but still remain within the City of Jacksonville rights-of-way along
Hemlock Street.
Once the new poles have been
installed, AT&T and Comcast will return to relocate their services from the
old poles to the new poles. Following this work, JEA will return to remove the
old poles. Please see the work area map below.
Tree Trimming and Vegetation Management
Proper vegetative clearance is required around JEA poles and facilities to allow the project to move forward. The vegetative management objectives are to enhance the benefits and mitigate the hazards of both the electrical service and existing tree canopy. JEA tree crews receive additional training on how to maintain sensitive tree canopies and target new growth approaching JEA lines (the line at the top of most utility poles).
Learn more about out goal of balancing a tree's health with safety and electric reliability. Customers are encouraged to contact JEA Tree Care at (904) 665-6050 or at JEATreeCare@JEA.com with any questions they may have regarding trees and utilities.
Restoration of the Project Area
Restoration of the project area will typically take place 2-3 weeks after the new lines have been installed, tested and cleared for use. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.
Even Better Power Reliability
JEA's state-of-the-art technology identifies customers and neighborhoods in need of electric reliability improvements.
Contact
-
If you have any questions about the Hemlock Street Electric Improvement Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.