Hendricks Avenue Well #8 Rehabilitation Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-06-14
Anticipated End Date: 2021-08-31

Normal working hours are Monday through Friday, 7:00 a.m. to 5:00 p.m. 

Additionally, crews were required to conduct 24-hour construction operations on the dates listed below. Please note, as construction can often times be unpredictable, we may have to reschedule portions of the overnight work. We apologize in advance for any inconveniences or disruptions caused by this construction work or any potential changes.

24-HOUR WORK DATES:

  • Anticipated Start Date:  June 28, 2021*
  • Estimated Completion Date:  July 2, 2021*

Project Objective

JEA rehabilitated an existing potable water well located at 2782 Southwood Lane in the San Jose Park area. This well is one of over 141 active wells that are a part of JEA’s regional water supply transmission system. Once completed, this well will improve our system’s overall water availability and reliability, while continuing to provide a robust water supply throughout JEA’s service territory.  

Learn more about JEA’s drinking water system/ 

Construction Conditions

Construction activities will take place on JEA’s property and within the City of Jacksonville’s rights-of-way, easements and roads.  

Hendricks Well 8 Rehab Project Map